- Contract Amount
- $109,000.00
- Project Type
- Lighting Retrofit
- Project Owner
- Del Monte Produce
- Cost Savings
- $32,000 Annually
- Fixtures Replaced
- 350
- Electrical Contractor
- FSG
Del Monte Produce Camden, New Jersey
Case Study
Del Monte Produce desired to upgrade the lighting systems in their Camden, New Jersey, warehouse. FSG was selected for this project.
Challenge
Del Monte Produce desired to upgrade the lighting systems in their Camden, New Jersey, warehouse. FSG was selected for this project.Solution
This project involved the upgrade of some 265 400W metal halide fixtures in the warehouse, as well as 78 fixtures in the attached office space. In addition, 480W vaportight TSHO fixtures designed for wash-down service were also upgraded. In the offices, T12 recessed fixtures were updated with new reflectors, electronic ballasts, and T8 lamps. The project resulted in annual energy savings of more than $32,000 per year, and a total payback time of just over one year.FSG projects consistently deliver excellence for our customers, for our employees, and for the communities we serve.
We see each project as an opportunity to embrace our mission and provide superior value through quality products, service, and support.
Let's Talk
Fill out the form and we’ll schedule a call to talk through a custom solution for you.
Or call us at
888-215-1336